Abstract:During the construction of the rubber dam pumping station, the excavation depth is large, and the groundwater level is relatively high compared to the foundation base surface, as well, it is influenced by factors such as foundation settlement and concrete shrinkage. Therefore, the seepage and water leakage in the pumping station are common problems in the actual construction process. This will lead to the corrosion of the reinforced concrete structure and affect the structural safety. Taking the construction of the pumping station of Qingkou River rubber dam in Junan County as an example, this article analyzes the common problems in the construction process of the pumping station. Starting from the aspects of drainage measures before construction, rigid waterproofing, flexible waterproofing, construction joints, and leakage at the pipes passing through the wall, it proposes treatment measures to make the actual construction process of the pumping station safer and more reliable, providing a reference for similar construction projects.