Abstract:In recent years, the Longtanhe Reservoir has encountered problems such as reduced seepage preventionperformance of the upstream anti-seepage face slab,high phreatic line in the dam body, and fault leakage. Based on thegeological survey and test data of the reservoir, parameter inversion was carried out, and finite element calculations wereperformed on the dam cross-sections of each dam segment to evaluate the seepage safely and seepage stability of the dam.The resuls show that the phreatic line of the dam body is signilicantly higher than the elevation of the dam drainagegallery, and the uplift pressure of the dam foundation drainage holes is relatively high; the seepage happens in the dambody,and the seepage gradient near the bedrock in the dam heel area is large,so that the seepage stabilily does not meetthe requirements; the rock mass fractures of the F1 fault in the dam foundation have undergone seepage failure, posingserious seepage salely hazards, and the seepage stability of the dam is poor.