Abstract:Aiming at prominent water level backwater in flood seasons, occasional urban waterlogging and insufficient capacity of drainage facilities in the urban section of Laoyunhe River in Jining, this paper takes the EPC expansion and reconstruction project of Shifo Drainage Pumping Station in Taibai Lake New Area as an example. Combined with project site conditions and water level characteristics, key technical measures for expansion and reconstruction of drainage pumping stations along the urban section of Laoyunhe River are proposed. Practice shows that after the refined reconstruction project is implemented, the actual drainage capacity of the pumping station is increased to 49 m3/s, the flood control and drainage standard of the urban Laoyunhe River is effectively upgraded to a 20-year return period, the risk of waterlogging in low-lying urban areas is greatly reduced, and the water environment operating conditions of the river are improved significantly.